dandelion

Creekside Run | Interactive Site Map

Ashford Homes · Frederick, MD · Data as of July 13, 2026 report
← Back to Dashboard
Crew Flow Street layout is representative — drops onto the real plat map when available.
CREEKSIDE RUN DRIVE

Legend

Commissioned
In Progress
Blocked / On Hold
Permitting in Process
Pre-Construction
🛠Drilling Crew position
🔧GLC Crew position
HVAC Sub position
Held movement (no dispatch)
Planned crew movement

The Path to Aug 15 — Flow of Success

Lots 1, 3, 5, 6 commissioned. Four of eight milestone homes closed out on time.
Complete
Close out Lot 2. Glycol QA resolved, system startup Jul 14 → 5 of 8.
Jul 14
Verify Lot 7 bore stakes before 7 AM, keep drilling on pace. One bore per working day, on track for Aug 14 commission.
Jul 13 EOD → ongoing
Unblock Lot 4. Pressure test photos → GLC resumes → heat pump install (confirm procurement + HVAC sub availability in parallel).
This week
Lot 8 permit decision — the critical path. Permit by Jul 16 → drill on time, Aug 15 holds. Permit Fri Jul 17 → drill Jul 21, 5-day slip, escalate to Ashford. Crew held off Lot 8 until permit is in hand; site pre-staged to drill same day it clears.
Jul 16–17
Sequence the handoffs. Lot 7 drilling → GLC → HVAC with no idle crew days; Lot 8 follows the same chain compressed.
Jul 17 – Aug 15
Aug 15: 8 homes fully commissioned. Lots 9–12 continue on builder's revised schedule (outside milestone scope).
Milestone